This project and the new objectives
have to take into account the evolution of the market. We
have carried out an comprehensive study and have opted for
a structure which is geared to future growth, wich from
the outset will enable us to expand the site progressively
in line with our needs.
We have constructed an easily accessible rigid central structure
using a technique based on a mix of metal and concrete on
which a series of individual units have been installed at
different levels, wich are also rigid to bear the weight
of the reactors and the material.
|
|
The unit as a whole
has been housed underneath a metal framework covered with light-weight
insulating panels. The basic configuration is the central structure
which is 42 m long, 8 m wide and 22 m high, with on one side a unit
for offices with measures of 6 m by 12 m, behind which there are
3 production units each measuring 12 m by 12 m on the ground floor.
Initially only the first part has been equipped, namely with 4 reactors
of 4500 L, 2 crystallizing dishes of 6300 L and 2 dryers.
The 2 other units will be equipped in line with needs and each of
them will be capable of taking material with a capacity of 2 x 10.000
L per unit and 4 x 6300 L per unit.
|
| Based on a central structure
with several levels which can accomodate different production units
to be added progressively. |
 |
 |
... |
The production units can be adapted
to our requirements.
The roof and facades covering the structure are made from
prefabricated insulating sections which can be readily dismandled.
|
|
|
|